KKH Phase II (Thakot -Havelian Section)

Project Name: KKH Phase II (Thakot -Havelian Section)

Project Description: Envisaging Improvement and widening of KKH Section of 440 Km from Raikot to Islamabad. The scope also includes provision of bridges, culverts and other allied facilities.

Length: 440 km

  • Thakot-Havelian (118) is in early harvest Project category and it is in implementation phase after siging of commercial and financial agreements.
  • Cost of Thakot-Havelian Section: US $ 1305 Million

Responsibility:

      Proposing Agency: Ministry of Communications

      Implementing Agency: National Highway Authority

      Supervising Agency: Ministry of Communications, Government of Pakistan

Contractor: CRBC , CCCC

Implementation Modality: EPC

Location:  Gilgit Baltistan & KPK  

Estimated Cost (US $ Million) : 1,305

Financing: Financing possibly through GCL.

Project Progress Update:

  • Contractor mobilized. Work commenced in September, 2016. To be completed by March, 2020
  • Havelian- Abbotabad-Mansehra (40 KM) section will be completed by May, 2018